New Market and tower Giridih
Saturday, 20 December 2014
Work Progress
31.12.14
27.12.14
PCC WORK 25.12.2014
LIFT AREA
Sand Filling Work
Thursday, 11 December 2014
Foundation Plinth work
Beam PCC base work begins 03.12.2014
Base work progresses 04.12.14
Beam work begins 06.12.2014
1st beam frame work complete 08.12.14
Work Status 10.12.14
Brick Shuttering 10.12.14
12.12.14
15.12.14
Septic tank location
Site preparation work/ excavation
Excavation work started.
1st Layer excavated
Final Excavation and leveling done manually
Entrance 27.11.14
Introduction
Site photos from ongoing construction of Market and Tower at Padam Chowk, Giridih are updated here!!